HOME/INTRO
HISTORY
DEMOLITION
RECONSTRUCTION EPILOGUE
Disclaimer: This is an unofficial site. It is not affiliated with or endorsed by CDOT, RTD, or the T-REX Project.
This page has a lot of photos. It will take a while to load.
Once the Steele Street Bridge had been demolished, the reconstruction effort would begin. The general process to rebuild the bridge proceeded in these steps:
|
Once the caissons at each end of the bridge had been drilled and poured, the abutments could be built on top of them. The abutments are basically shelves on which the ends of the girders sit. Wood formwork is put in place to form the abutment and the rebar placed, and then concrete is poured into the formwork to create the abutment. |
While the two abutments support the girders at each end of the bridge, a pier supports them in the median of I-25. The pier was constructed by first drilling three caissons, then forming a pier cap on top of it. A pier cap is basically a large horizontal concrete beam on which the girders sit. |
|
Once both abutments and the center pier were complete, the next major milestone could be accomplished: Setting the girders. The girders for the Steele Street Bridge are standard concrete "bulb-T" girders, precast and prestressed in a factory and then trucked to the site. There, they are lowered into place by a crane during an overnight total closure of I-25. This was done May 14. |
Once the girders were in place, the next order of business was to create the deck on which the vehicles drive. The deck is a cast-in-place concrete slab on top of the girders. Before the deck can be poured, however, an intricate rebar system has to be laid. |
The two photos below are of workers putting in the rebar system for the deck (15Jun02). The steel rebar, normally dark, is green because it is epoxy coated to keep it from rusting.
After all of the rebar for the deck had been laid, a deck pour would be done. The deck pour was a massive one-night operation where concrete was trucked in constantly so that the concrete for the entire deck of the bridge was poured. The deck pour was done June 19. |
|
In July and early August, work concentrated on the final work to get the bridge ready for opening. This included forming and pouring the concrete approach slabs, reconstructing the asphalt approaches and curb on the street which equipment had torn up, putting in railing, fencing, and lighting, and forming and pouring six "monuments" that add an aesthetic element to the bridge. |
The bridge was complete enough to open it to pedestrian traffic on August 6. The next day the temporary pedestrian bridge was removed. The Steele Street Bridge opened to vehicle traffic the morning of Monday, August 19, 2002, 224 days after it had closed. Go to the Epilogue for photos the completed bridge, as well as a time lapse movie showing the work progressing. |
Steele Street Bridge:
HOME/INTRO
HISTORY
DEMOLITION
RECONSTRUCTION EPILOGUE
Continue:
Page created 19 April 2002
Last updated 21 September 2002